# Frisby Road Roundabout: Construction Update

 

    ![IMG 0030](data:image/svg+xml;charset=utf-8,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%271920%27%20height%3D%271079.8650168729%27%20style%3D%27background%3Atransparent%27%2F%3E)

    

 

    

     

Recent works have seen the **deep lift asphalt** completed on schedule, with the **final wearing course asphalt** still to come. Meanwhile, **power lines are set to be undergrounded in November**, marking another key milestone for the project.

 

 [  ![IMG 0028](data:image/svg+xml;charset=utf-8,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%271920%27%20height%3D%271079.8650168729%27%20style%3D%27background%3Atransparent%27%2F%3E)

  ](https://d2tpafjlg316w2.cloudfront.net/eyJidWNrZXQiOiJsYW5zZXItcHJvZC1pbWFnZXMiLCJrZXkiOiJhc3NldHMvaW1hZ2VzL21pcmF2YWxlL0NvbnN0cnVjdGlvbi1VcGRhdGVzL0ZyaXNieVJvYWRPY3QyNS9JTUdfMDAyOC5KUEciLCJlZGl0cyI6eyJyZXNpemUiOnsiZml0IjoiY292ZXIifSwid2l0aE1ldGFkYXRhIjp0cnVlLCJ0b0Zvcm1hdCI6ImpwZWciLCJqcGVnIjp7InF1YWxpdHkiOjgwLCJwcm9ncmVzc2l2ZSI6dHJ1ZSwib3B0aW1pc2VDb2RpbmciOnRydWUsInRyZWxsaXNRdWFudGlzYXRpb24iOnRydWUsIm92ZXJzaG9vdERlcmluZ2luZyI6dHJ1ZX19fQ==)- [  ![IMG 0029](data:image/svg+xml;charset=utf-8,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%271920%27%20height%3D%271079.8650168729%27%20style%3D%27background%3Atransparent%27%2F%3E)
    
      ](https://d2tpafjlg316w2.cloudfront.net/eyJidWNrZXQiOiJsYW5zZXItcHJvZC1pbWFnZXMiLCJrZXkiOiJhc3NldHMvaW1hZ2VzL21pcmF2YWxlL0NvbnN0cnVjdGlvbi1VcGRhdGVzL0ZyaXNieVJvYWRPY3QyNS9JTUdfMDAyOS5KUEciLCJlZGl0cyI6eyJyZXNpemUiOnsiZml0IjoiY292ZXIifSwid2l0aE1ldGFkYXRhIjp0cnVlLCJ0b0Zvcm1hdCI6ImpwZWciLCJqcGVnIjp7InF1YWxpdHkiOjgwLCJwcm9ncmVzc2l2ZSI6dHJ1ZSwib3B0aW1pc2VDb2RpbmciOnRydWUsInRyZWxsaXNRdWFudGlzYXRpb24iOnRydWUsIm92ZXJzaG9vdERlcmluZ2luZyI6dHJ1ZX19fQ==)
- [  ![IMG 0030](data:image/svg+xml;charset=utf-8,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%271920%27%20height%3D%271079.8650168729%27%20style%3D%27background%3Atransparent%27%2F%3E)
    
      ](https://d2tpafjlg316w2.cloudfront.net/eyJidWNrZXQiOiJsYW5zZXItcHJvZC1pbWFnZXMiLCJrZXkiOiJhc3NldHMvaW1hZ2VzL21pcmF2YWxlL0NvbnN0cnVjdGlvbi1VcGRhdGVzL0ZyaXNieVJvYWRPY3QyNS9JTUdfMDAzMC5KUEciLCJlZGl0cyI6eyJyZXNpemUiOnsiZml0IjoiY292ZXIifSwid2l0aE1ldGFkYXRhIjp0cnVlLCJ0b0Zvcm1hdCI6ImpwZWciLCJqcGVnIjp7InF1YWxpdHkiOjgwLCJwcm9ncmVzc2l2ZSI6dHJ1ZSwib3B0aW1pc2VDb2RpbmciOnRydWUsInRyZWxsaXNRdWFudGlzYXRpb24iOnRydWUsIm92ZXJzaG9vdERlcmluZ2luZyI6dHJ1ZX19fQ==)
- [  ![IMG 0031](data:image/svg+xml;charset=utf-8,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%271920%27%20height%3D%271079.8650168729%27%20style%3D%27background%3Atransparent%27%2F%3E)
    
      ](https://d2tpafjlg316w2.cloudfront.net/eyJidWNrZXQiOiJsYW5zZXItcHJvZC1pbWFnZXMiLCJrZXkiOiJhc3NldHMvaW1hZ2VzL21pcmF2YWxlL0NvbnN0cnVjdGlvbi1VcGRhdGVzL0ZyaXNieVJvYWRPY3QyNS9JTUdfMDAzMS5KUEciLCJlZGl0cyI6eyJyZXNpemUiOnsiZml0IjoiY292ZXIifSwid2l0aE1ldGFkYXRhIjp0cnVlLCJ0b0Zvcm1hdCI6ImpwZWciLCJqcGVnIjp7InF1YWxpdHkiOjgwLCJwcm9ncmVzc2l2ZSI6dHJ1ZSwib3B0aW1pc2VDb2RpbmciOnRydWUsInRyZWxsaXNRdWFudGlzYXRpb24iOnRydWUsIm92ZXJzaG9vdERlcmluZ2luZyI6dHJ1ZX19fQ==)
 

 

The roundabout is **on track for completion by late 2025**, and once finished, it will make travelling to and from Miravale even easier and safer for Angle Vale residents and visitors alike.

 

Stay tuned for more updates as we continue building a connected, thriving community at Miravale.

 

 

   [##  Not sure where to start?   
 We’d love to chat to you. 

##  Not sure where to start? We’d love to chat to you. 

 Get in touch 

 

 ](https://www.lanser.com.au/contact) 

 

 

     [   All news ](https://www.lanser.com.au/news) Lanser October 26, 2025 

# Frisby Road Roundabout: Construction Update

 

    ![IMG 0030](data:image/svg+xml;charset=utf-8,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%271920%27%20height%3D%271079.8650168729%27%20style%3D%27background%3Atransparent%27%2F%3E)

    

 

    

     

Recent works have seen the **deep lift asphalt** completed on schedule, with the **final wearing course asphalt** still to come. Meanwhile, **power lines are set to be undergrounded in November**, marking another key milestone for the project.

 

 [  ![IMG 0028](data:image/svg+xml;charset=utf-8,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%271920%27%20height%3D%271079.8650168729%27%20style%3D%27background%3Atransparent%27%2F%3E)

  ](https://d2tpafjlg316w2.cloudfront.net/eyJidWNrZXQiOiJsYW5zZXItcHJvZC1pbWFnZXMiLCJrZXkiOiJhc3NldHMvaW1hZ2VzL21pcmF2YWxlL0NvbnN0cnVjdGlvbi1VcGRhdGVzL0ZyaXNieVJvYWRPY3QyNS9JTUdfMDAyOC5KUEciLCJlZGl0cyI6eyJyZXNpemUiOnsiZml0IjoiY292ZXIifSwid2l0aE1ldGFkYXRhIjp0cnVlLCJ0b0Zvcm1hdCI6ImpwZWciLCJqcGVnIjp7InF1YWxpdHkiOjgwLCJwcm9ncmVzc2l2ZSI6dHJ1ZSwib3B0aW1pc2VDb2RpbmciOnRydWUsInRyZWxsaXNRdWFudGlzYXRpb24iOnRydWUsIm92ZXJzaG9vdERlcmluZ2luZyI6dHJ1ZX19fQ==)- [  ![IMG 0029](data:image/svg+xml;charset=utf-8,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%271920%27%20height%3D%271079.8650168729%27%20style%3D%27background%3Atransparent%27%2F%3E)
    
      ](https://d2tpafjlg316w2.cloudfront.net/eyJidWNrZXQiOiJsYW5zZXItcHJvZC1pbWFnZXMiLCJrZXkiOiJhc3NldHMvaW1hZ2VzL21pcmF2YWxlL0NvbnN0cnVjdGlvbi1VcGRhdGVzL0ZyaXNieVJvYWRPY3QyNS9JTUdfMDAyOS5KUEciLCJlZGl0cyI6eyJyZXNpemUiOnsiZml0IjoiY292ZXIifSwid2l0aE1ldGFkYXRhIjp0cnVlLCJ0b0Zvcm1hdCI6ImpwZWciLCJqcGVnIjp7InF1YWxpdHkiOjgwLCJwcm9ncmVzc2l2ZSI6dHJ1ZSwib3B0aW1pc2VDb2RpbmciOnRydWUsInRyZWxsaXNRdWFudGlzYXRpb24iOnRydWUsIm92ZXJzaG9vdERlcmluZ2luZyI6dHJ1ZX19fQ==)
- [  ![IMG 0030](data:image/svg+xml;charset=utf-8,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%271920%27%20height%3D%271079.8650168729%27%20style%3D%27background%3Atransparent%27%2F%3E)
    
      ](https://d2tpafjlg316w2.cloudfront.net/eyJidWNrZXQiOiJsYW5zZXItcHJvZC1pbWFnZXMiLCJrZXkiOiJhc3NldHMvaW1hZ2VzL21pcmF2YWxlL0NvbnN0cnVjdGlvbi1VcGRhdGVzL0ZyaXNieVJvYWRPY3QyNS9JTUdfMDAzMC5KUEciLCJlZGl0cyI6eyJyZXNpemUiOnsiZml0IjoiY292ZXIifSwid2l0aE1ldGFkYXRhIjp0cnVlLCJ0b0Zvcm1hdCI6ImpwZWciLCJqcGVnIjp7InF1YWxpdHkiOjgwLCJwcm9ncmVzc2l2ZSI6dHJ1ZSwib3B0aW1pc2VDb2RpbmciOnRydWUsInRyZWxsaXNRdWFudGlzYXRpb24iOnRydWUsIm92ZXJzaG9vdERlcmluZ2luZyI6dHJ1ZX19fQ==)
- [  ![IMG 0031](data:image/svg+xml;charset=utf-8,%3Csvg%20xmlns%3D%27http%3A%2F%2Fwww.w3.org%2F2000%2Fsvg%27%20width%3D%271920%27%20height%3D%271079.8650168729%27%20style%3D%27background%3Atransparent%27%2F%3E)
    
      ](https://d2tpafjlg316w2.cloudfront.net/eyJidWNrZXQiOiJsYW5zZXItcHJvZC1pbWFnZXMiLCJrZXkiOiJhc3NldHMvaW1hZ2VzL21pcmF2YWxlL0NvbnN0cnVjdGlvbi1VcGRhdGVzL0ZyaXNieVJvYWRPY3QyNS9JTUdfMDAzMS5KUEciLCJlZGl0cyI6eyJyZXNpemUiOnsiZml0IjoiY292ZXIifSwid2l0aE1ldGFkYXRhIjp0cnVlLCJ0b0Zvcm1hdCI6ImpwZWciLCJqcGVnIjp7InF1YWxpdHkiOjgwLCJwcm9ncmVzc2l2ZSI6dHJ1ZSwib3B0aW1pc2VDb2RpbmciOnRydWUsInRyZWxsaXNRdWFudGlzYXRpb24iOnRydWUsIm92ZXJzaG9vdERlcmluZ2luZyI6dHJ1ZX19fQ==)
 

 

The roundabout is **on track for completion by late 2025**, and once finished, it will make travelling to and from Miravale even easier and safer for Angle Vale residents and visitors alike.

 

Stay tuned for more updates as we continue building a connected, thriving community at Miravale.

 

 