September 24, 2025
Exciting progress continues at The Vines Collection, with both internal and external works moving steadily ahead. Here’s the latest construction news as we move closer to welcoming our new residents:
Internal Works
- Final painting completed in six homes
- 2nd fix carpentry defects rectified
- Quads installed around eaves and alfresco ceilings
- Alfresco ceiling paintwork completed
- 2nd fix plumbing fully completed (shower screens, toilets, basins, mirrors etc installed)
- Built-in robe installation completed
- Stair handrails installed
- Flooring installation underway
- Final paint touch-ups to be completed
External Works
- Carport concreting complete
- Paving works have commenced
- Fencing works have commenced
- Garage doors to be installed for all 12 dwellings
- Final external paint touch ups
With these key milestones underway, The Vines Collection is taking shape beautifully — inside and out. We look forward to sharing further updates as your new home continues to come to life. If you have any questions, please don’t hesitate to get in touch with our team.